Revision #41 week ago by Priya AnandAdded the mandatory postmortem step for SEV-1/SEV-2 incidents.

No field changes — this was the initial version of this item.

Revision #39 months ago by Priya AnandTightened the SEV-1 response target after the Q1 incident review.
FieldPrevious ValueNew Value
SEV-1Customer data unavailable or at risk of loss — < 10 min responseCustomer data unavailable or at risk of loss — Immediate response
Revision #22 years ago by Barry JenkinsIntroduced the four-tier severity model to replace the old binary up/down classification.

No field changes — this was the initial version of this item.

Revision #14 years ago by Barry JenkinsInitial page created.